Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Irrigation and Water Resources Management Project
Pokhara, Kaski
Notice of Intention to Award Contract
Date of Publication: 2081-12-20 B.S. (2nd April, 2025)
Pursuant to Clauses 27, Sub-Clauses 2 of Public Procurement Act, 2063 (including Amendment), this is hereby notified to all concerned bidders who submitted their bid for the contracts mentioned below that the following listed lowest evaluated substantially responsive bidder has been selected to award the contract.
S. N.
1
Contract No.
Description of Works
Lowest Evaluated Substantially Responsive Bidder
Bid Price NRs. (Including VAT & PS)
IWRMP-KASKI/MYAGDI-SINGHA/NCB/WORKS/15/081-82
Construction of Composite Concrete Retaining Wall with Gabion wall as well as Launching Apron at L/S of Myagdi River, D/S of Jholunge Pool, Singha, Masaar Basti, Beni Na. Pa.-04, Myagdi.
M/S RRC-GEMI JV, Resunga - 01, Gulmi
2,71,90,845.15
IWRMP-KASKI/MYAGDI-BACKSIDEOFDAO/NCB/WORKS/16/081-82
Construction of Composite Concrete Retaining Wall with Gabion wall as well as Launching Apron at L/S of Myagdi River, D/S of Truss Bridge (Back Side of DAO), Beni-07, Myagdi.
M/S Rupal Supreme Construction, Neelkantha-03, Dhading
4,21,59,699.19
IWRMP-KASKI/PARBAT-AARMADIANDJALJALA/NCB/WORKS/17/081-82
Construction of Composite Concrete Retaining Wall with Gabion wall as well as Launching Apron at L/S of Kaligandaki River, Aarmadi, Kusma-04 and Backside of Jaljala RM Office, Jaljala-04, Parbat
M/S Nakul-BRT-Saya JV, Dang
2,96,34,838.43
4
IWRMP-KASKI/PARBAT-WAYTOBAURA/NCB/WORKS/18/081-82
2
3
Construction of Composite Retaining Wall with Rod Anchorage at U/S of Suspension Bridge, Way to Baura, Jaljala-03, Parbat.
M/S Gopi-Sahana JV, Ghorahi - 15, Dang
2,09,89,731.22
Project Manager
Source: Rajdhani