Nepal Electricity Authority PAL ELECTRICITY AUTHORITY

Nepal Electricity Authority Bagamati Province Division Office, Hetauda

NEA/BPDOH/2082/083-01  Design, Supply, Delivery, Installation, Testing & Commissioning of JAGATPUR MADI 33 kV Underground Sub Transmission Line in Chitwan National Park Area. 1. M/S. Waiba Infratech Pvt. Ltd., Swayambhu-15, Kathmandu. [new
2. M/S. Renu Construction Company Pvt. Ltd./Paramount Construction Pvt. Ltd. JV, Lalitpur.
3. M/S. Sarada and Sumnima International/Vishan Construction JV, Nilkanth-5, Dhading.
4. M/S. Energetic Nepal Pvt. Ltd./Natural Resource Industries Pvt.Ltd., JV, Mitranagar 29, Kathmandu.
5. M/S. Jaya Durge Infra Engineering Pvt.Ltd./O.S. Engineering Nirman Sewa Pvt. Ltd. JV, Nilkanth-3, Dhading.