Government of Nepal

Ministry of Physical Infrastructure and Transport

Roads Department

Pushpalal (Mid-Hill) Highway Planning Directorate Pushpalal (Mid-Hill) Highway Planning Office Phidim, Panchthar

 

Very important information regarding  termination of the contract

 

 

Notice Published Date : 2082/07/17

In the contracts under construction under this office, despite repeated written/verbal instructions/instructions to the concerned construction entrepreneur to complete the work on time, there is a suspicion that the work will/will not be completed on time. Despite the commitment to complete the work on time during the repeated extensions in the past, the progress is as per the self-declared work plan schedule. Due to the lack of mobilization of sufficient manpower and resources, the expected progress has not been made and the possibility of completing the work on time seems low. In fact, the official representative of the Planning Office is present at the Planning Office along with the revised work plan schedule after mobilizing sufficient resources/manpower to ensure the reliability of completing the work within 15 (fifteen) days of the publication of this notice. This notice has been published. If it is seen that the construction/repair work has not progressed as expected by mobilizing the necessary resources/manpower within that period in the said work area under regular monitoring, the contract agreement conditions, Public Procurement Act-2063, Attention is drawn to the recommendation to confiscate the security deposit, terminate the contract, and blacklist as per the attractive provisions of the Regulations-2064.

Therefore, if there is any basis for not terminating the contract, the mentioned construction entrepreneur is informed that a final opportunity has been provided to submit a dynamic or clarification including a future action plan along with clear evidence. Reder

details

No. No.

Contract no.

Job description

Name of builder

Agreement Date:

Extended

Work to be completed (including more)

MIDHLKTM/3371384/071/072-108

Blacktop & Roadway Improvement Works (Ch. 83+000-93+000) at Terathum District

Contech/Gauri Parvati/Koshi & Neupane J.V.

1

2072/05/31

7 times

2082/08/27

MIDHLKTM/337011144/077/078-101

Widening and Upgrading of Puspalal (Midhill) Highway along Chiyabhangyang-Ganeshchowk Section (ch. 0+000 to 16+000)

2

Roshan/Shiva Shakti J.V.

2077/10/19

3 times

2082/09/29

MIDHLKTM/337011144/077/078-102

Widening and Upgrading of Puspalal (Midhill) Highway along Chiyabhangyang-Ganeshchowk Section (ch. 16+000 to 33+000)

3

Santoshi/Shiva Shakti J.V.

2077/10/19

3 times

2082/09/29

MIDHLKTM/3371384/073/074-104 (Re)

4

Construction of Motorable Bridge at Khanduwa Khola along Ganeshchowk-Chiobhanjyang Road, Pachthar (RCC 1*20m)

Plant/Galva J.V.

2074/02/31

7 times

2082/09/29

5

MIDHLKTM/3371384/072/073-202

Earthworks, Structure works, Cross-Drainage Works and Pavement Works at Hile-Leguwa Sector (Chainage 13+000 to 26+000)

Routha/Santoshi/Biruwa J.V.

2072/12/02

7 times

2082/06/23