Shri Sthapathi Directorate, Jangi Adda, Kathmandu
Notice of invitation for electronic bidding
Notification No. 2082/83/03 (first published on 2082/04/15)
Bids have been invited for
construction work at various locations of the Nepal Army in the fiscal year 2082/83.
Detailed information regarding the bid has also been placed on the website of the Public Procurement Monitoring Office http://www.bolpatra.gov.np/egp. This notice has been published for the interested and eligible bidders for the construction work to submit their bids through e-GP.
Details of tenders
C. No.
unit
3
District/Place
local news
1 Shri Nepali Military Academy
Kharipati Barracks, Bhaktapur
2
Mr. No. 2 Ban and Environmental Protection Group
Elephant Barracks, Nawalparasi
Mining
Shree Counter Insurgency and Jungle Warfare School
Amlekhgunj, Bara
Shri Purvi Pritana Training School
Letang, Morang
Shri Sainik Command and Staff College
Shivpuri, Kathmandu
6 Shri No.19 Vahini Adda
Ghorahi Barracks, Dang
Shri No.19 Bahini Adda
Ghorahi Barracks, Dang
Mr. Chandidal Gan
Salle Barracks, Rukum West
9 Shri Bhairav Gana
Gajuri Barracks, Dhading
10
Shri Durgadal Gulm
Tokme Barracks, Taplejung
Program details
Cost Estimate (including VAT)
Ka.
Multi-Story Dining Hall (G+1)
Residential area (G+1)
Foreign Student Residence (G+1)
4
Residential area (G+1)
5
young cook
1,80,00,000.00
Vahinipati residence
1,49,99,450.82
1X 20 Bed Female Soldier's Shelter (G)
7
1,44,99,528.05
To complete the remaining construction work of the official residence
8
61,47,359.19
Abode of Ganapati
1,34,27,376.51
Padik Kitchen and Dining Hall (G)
1,50,67,780.93
conditions
1. As per Sub-section (2) of Section 10 of the Public Procurement Act, 2063, the bidders must have performed the work satisfactorily (no administrative action such as warning letter, work improvement letter, contract suspension, predetermined compensation, contract termination, recommendation for blacklisting, etc.) if they have carried out construction work in the bodies under the Nepal Army in the past 2 fiscal years (2079.80 and 2080.81).
2. The bidder shall visit the site at his own expense. In case of not visiting the site, a commitment letter stating "I agree/agree to carry out the construction work wherever and in whatever condition the construction site is" must be submitted while submitting the bid.
3. As per Sub-rule 1 (c) of Rule 123 of the Public Procurement Regulations, 2064, the concerned construction entrepreneur will be paid the running bill on the basis of completion of the milestones set for the construction work. In addition, the concerned construction entrepreneur will have to mandatorily submit the necessary documents including the bill/invoice for payment within 15 days of completion of each milestone.
4. In accordance with subsections (7) and (8) of Section 59 of the Public Procurement Act, 2063, if the construction entrepreneur does not commence the work as per the agreement, if he/she abandons the work before it has started or if the work does not progress as per the agreement, such agreement shall be terminated at any time and the entire security shall be forfeited. It is also notified that any amount required to complete the remaining work as per the agreement due to the termination of the agreement shall be recovered from the construction entrepreneur who does not perform the work as per the agreement as a government due.